Homepage
Project Description
The Hollywood Florida Community Redevelopment Agency Plan identified redevelopment objectives which include: promoting redevelopment and eliminating the causes of physical and economic blight, ensuring sanitary and safe conditions through infrastructure improvements, improving the circulation for pedestrians, bicyclists and motorists, upgrading existing public recreation facilities and expanding recreation opportunities.
The goal is to enrich the visual and functional quality of the streetscape for all user groups, preserve and maintain natural resources. The City of Hollywood/CRA identified the Hollywood Boulevard Streetscape as a project that will enrich the visual and functional quality of the Hollywood Boulevard area in the Downtown.
Project Images
Location and Boundary
Project Documents
Crosswalk Schedule for Hollywood Blvd
Coffee with the Crew
Thursday, May 30 9 am - 10 am
Toby's Billiards
2004 Hollywood Boulevard
BCI Project Information Brochure - 06/22/23
Coffee with the Crew
Thursday, April 18 * 9:00 am - 10:00 am
Burkhardt Construction
1934 Hollywood Boulevard, Suite 200
Simplified Detour For Southside Between 19th and 20th - Incl. South Side of 19th and H.W. Blvd. Intersection
Simplified Detour For Southside Between 19th and 20th - Incl. N. 19th Ave. Between Tyler St. and Hollywood Blvd
Simplified Detour For Southside Between 19th and 20th - Incl. N. 20th Ave. Between Tyler St. and Hollywood Blvd
Important Dates
*Updated* Important Dates
We have updated the information below. Please review it for changes!
WEEK OF 8/12/2024:
· The southside (eastbound) of Hollywood Blvd. will be closed between 21st Avenue and 19th Avenue for construction.
· S. 20th Avenue between Harrison and Hollywood Blvd. will be closed since the southside of the intersection at Hollywood Blvd. and 20th will be under construction.
· Access to the alleyway between Harrison and Hollywood Blvd. on S. 20th Avenue will remain open.
· North and South 19th and 20th Avenues will be closed intermittently as we mill and pave during this week.
· Center median diagonal parking stalls will be closed intermittently as we pave.
· We should be able to reopen all roadways by 8/16/2024.
WEEK OF 8/19/2024:
· Final paving will be taking place on the north and south sides of Hollywood Blvd. between 21st and Young Circle.
· We will keep other parts of downtown open as we're finishing paving.
· Crosswalk construction on S. 20th Avenue, N. 19th Avenue, and half of the crosswalk at Hollywood Blvd. and 20th, NE side (orange highlight)
WEEK OF 8/26/2024:
· Final paving will be taking place on the north and south sides of Hollywood Blvd. between 21st and Young Circle.
· Crosswalk construction on N. 20th Avenue and S. 19th Avenue (yellow highlight)
· Open all roadways on 8/30/2024 for Labor Day Weekend.
WEEK OF 9/3/2024:
· Crosswalk construction on Hollywood Blvd. between 20th Avenue and 19th Avenue on the southside (green highlight).
· Southside of Hollywood Blvd. between 20th and 19th will be closed to traffic this week.
WEEK OF 9/9/2024:
· Crosswalk construction on Hollywood Blvd. northside between 19th and 20th Avenues. Partial crosswalk construction at 21st Avenue and west side of 20th Avenue (blue highlight).
· Northside of Hollywood Blvd. between 20th and 19th will be closed to traffic this week.
WEEK OF 9/16/2024:
· Crosswalk construction on northside of Hollywood Blvd. between 21st Avenue and 20th Avenue.
· Northside of Hollywood Blvd. between 21st Avenue and 20th Avenue will be closed to traffic this week.
WEEK OF 9/23/2024:
· Crosswalk construction on southside of Hollywood Blvd. between 21st Avenue and 20th Avenue. Crosswalk construction on the north and south sides of Hollywood Blvd. between 19th Avenue and Young Circle (red boxed areas).
· Southside of Hollywood Blvd. between 21st Avenue and 20th Avenue will be closed to traffic this week as well as the north and south sides of Hollywood Blvd. between 19th Avenue and Young Circle.
· Open all roadways 9/27.
Road Closure and Streetscape Updates 6/10/2024
ROAD CLOSURES:
- Southside of Hollywood Blvd. between 20th Avenue and 21st Avenue to be closed until late August, but will be open every weekend starting the weekend of July 4th.
- Based on feedback at the last Coffee with the Crew we will open the southside (eastbound lane) between 20th and 21st during the weekends starting the weekend of 7/4/2024.
- After the July 4th Holiday weekend, the road will be closed during the week (Monday through Friday) and will open on Friday afternoons and will remain open until Monday mornings.
STREETSCAPE UPDATE:
- Irrigation and Electrical Rough-in
- Installation of electrical handholes and pole bases
- Excavation/grading of roadway
- Subgrade for sidewalk area
- Excavating and pouring tree pit header curbs.
HOLLYWOOD BLVD. SOUTHSIDE BETWEEN 19TH AND 20TH:
- Paver installation
- Pressure cleaning and sealing pavers
- Roadway subgrade and limerock
- Pave roadway
- Install signs and stripe roadway and parallel parking stalls
- Furnishing installation
HOLLYWOOD BLVD. SOUTHSIDE BETWEEN 20TH AND 21ST:
- Asphalt repair to open a couple of the parking stalls
ROAD CLOSURE UPDATE:
- Southside of Hollywood Blvd. between 19th and 20th will open on 5/17/2024.
- The parallel parking stalls on the southside between 19th and 20th will remain closed until 5/24/2024 to finish pressure cleaning/sealing and final cleanup. Parallel parking stalls will open on 5/24/2024.
- The closure of the southside of Hollywood Blvd. between 21st and 20th will begin on Tuesday, May 28th, 2024 (The Tuesday after Memorial Day weekend)
Simplified Detour For Southside Between 19th and 20th - Incl. N. 20th Ave. Between Tyler St. and Hollywood Blvd
ROAD CLOSURES:
- Southside of Hollywood Blvd. between 20th Avenue and 19th Avenue to be closed until May 17th.
- N. 20th Avenue between Hollywood Blvd. and Tyler Street will be opened on 5/2/2024.
- Southside of the Hollywood Blvd. and 19th Avenue intersection will be closed beginning 5/6/2024.
- Parking areas on the south side of Hollywood Blvd. between 21st Avenue and 20th Avenue will be impacted for storm drainage installation beginning week of 5/6/2024.
- Southside of Hollywood Blvd. between 20th Avenue and 19th Avenue will be opened on 5/17/2024.
- Southside of Hollywood Blvd. between 21st Avenue and 20th Avenue will be closed for construction beginning 5/20/2024.
SCHEDULE/WORK UPDATE FOR WEEKS OF 5/6/2024 AND 5/13/2024:
- Subgrading sidewalk
- Continue pouring 12" radius bands
- Form and pour curbing for permeable parking areas
- Paver installation beginning on the east end and working west
- Subgrade and construction of the south side of the 19th Avenue intersection.
- Milling the diagonal parking stalls
- First lift of asphalt
- Pour flowable fill for paver base
- OPEN BLOCK ON 5/17/2024
ROAD CLOSURE UPDATES – 4/19/2024:
- Hollywood Blvd. from 20th Avenue to 19th Avenue to remain closed.
- N. 20th Avenue will be opened on Saturday at noon (4/20/2024) for northbound traffic. We'll close it again on Monday (4/22/2024) to continue work.
- N. 20th Avenue will be open by 5/3/2024.
- The southside of the 19th Avenue intersection will be closed on 5/6/2024 for construction until completion.
- Hollywood Blvd. between 19th Avenue and 20th Avenue will be completed and opened to traffic on 5/17/2024.
- Installation of storm drainage structures between 21st Avenue and 20th Avenue will begin 4/29/2024. Parking stalls will be impacted, but the road will remain open. We will patch the parking areas back so the car show can take place as scheduled.
Close southside of Hollywood Blvd. between 21st and 20th on 5/20/2024 for construction. This closure will be in place for 12 weeks.
Coffee with the Crew
Thursday, May 30 9 am - 10 am
Toby's Billiards
2004 Hollywood Boulevard
Project Start Date
May 8th, 2023
Merchant Meetings
Merchant Meeting
March 7th, 2023
Merchant Meeting
March 28th, 2023
Merchant Meeting
April 25th, 2023
Next Merchant Meeting
TBD
Public Meetings
Coffee with the Crew
April 18, 2024
CRA Commission Meeting Presentation
May 3rd, 2023
Groundbreaking Ceremony
May 3rd, 2023
Frequently Asked Questions
The construction phase is scheduled to start May 8, 2023.
The construction phase has an estimated duration of 17 months and an estimated completion date of September 30, 2024.
During construction temporary detours can be expected. Construction will take place in each phase both in the roadway and sidewalk. Noise and dust can be expected. Vibration and noise could be caused by heavy equipment. Coordination with stakeholders will be done in advance of each phase. Maintenance of traffic devices (the familiar orange cones) along with custom signage will be placed to inform motorists and pedestrians of areas where construction is taking place and advise on alternate routes.
You can call the project hotline at 561-781-0888, email LLiotta@hollywoodfl.org, or submit a question via the website using the form below.
Contact Us
For further information, please call the project hotline at 561-781-0888.
Or contact the Hollywood CRA:
Francisco Diaz Mendez, Project Manager | 954-924-2980 | FDiaz-Mendez@hollywoodfl.org